Project Complexity Dashboard

🎯 Project Complexity at a Glance

39 Demand Items
195 Phase Tasks
10⁷⁹ Assignment Combos
2.4x Capacity Overload

👥 Team Eligibility Matrix

Phase Mark Jerry Chhojun Andrew Hajra Available
Spec 2
Dev 3
Test 3
Deploy 3
Docs 2
⚠️ Critical Bottlenecks: Spec (2 people) and Docs (2 people) have severely limited resources

📊 Capacity vs Demand by Phase

Spec
89 pd
Dev
178 pd
Test
156 pd
Deploy
72 pd
Docs
52 pd
Spec: 84 pd max
Dev: 126 pd max

Red bars = Actual demand | Green lines = Maximum feasible capacity

📅 Team Capacity Heatmap (10-Week Window)

Week →
1
2
3
4
5
6
7
8
9
10
Mark
2d
2d
2d
4d
4d
6d
5d
4d
4d
4d
Jerry
2d
2d
2d
4d
5d
6d
4d
4d
4d
4d
Andrew
2d
2d
4d
4d
4d
5d
6d
4d
4d
4d
Chhojun
2d
2d
4d
5d
6d
4d
4d
4d
4d
4d
Hajra
2d
2d
4d
4d
4d
4d
5d
6d
4d
4d
Green = Normal capacity
Orange = Reduced capacity
Red = Overloaded

🎲 Scenario Analysis & Risk Assessment

🎯 Best Case Scenario (15% probability)

Outcome: All team members perform at peak efficiency, no unexpected delays, perfect task handoffs.
Timeline: 42 weeks | Resource utilization: 501/210 person-days (2.39x capacity)
Key assumption: Zero rework, optimal skill matching, no external dependencies

⚖️ Most Likely Scenario (60% probability)

Outcome: Mixed efficiency levels, 15-20% rework factor, typical bottleneck delays in Spec/Docs phases.
Timeline: 58 weeks | Resource utilization: 650/210 person-days (3.1x capacity)
Critical risks: Documentation backlog, specification review delays, testing queue buildup

🔥 Worst Case Scenario (25% probability)

Outcome: Significant skill mismatches, 30%+ rework, team member unavailability, scope creep.
Timeline: 85+ weeks | Resource utilization: 1,227/210 person-days (5.85x capacity)
Failure points: Spec bottleneck breakdown, cascading delays, quality compromises